Moonpool Support Frame for 7x Subsea Horizontal XT's

Our Experience

The Situation

A well management company was planning a 180-day plug and abandonment decommissioning campaign on a Semi-Submersible Drilling Rig, involving the retrieval of 7 subsea tree structures of two different types.

Before the campaign could proceed, Phase was engaged to verify that the equipment would physically work through the moonpool on that specific rig — fit, clearance, handling sequences, and interface compatibility across the moonpool area, Normar Carrier.

For subsea engineers and operators, the available space and handling equipment within a moonpool is not always fully understood ahead of a campaign. The consequences of discovering a physical conflict offshore — during a live decommissioning operation — are significant.

What Phase Established

Phase travelled to the rig and carried out a laser survey of the moonpool area, starboard laydown area, and handling equipment. Using scan data, 3d models, combined with equipment drawings, Phase carried out interface and clash checks, agreed deployment sequences and stacking assemblies, and identified all key interface locations.

During this process Phase identified that the subsea trees could not be lifted into the moonpool using the existing BOP Normar Carrier — a critical finding that would have been discovered offshore during a live campaign without this verification work.

The Consequence Addressed

A 180-day offshore P&A decommissioning campaign involving 10 subsea tree retrievals.

Any interface conflict discovered offshore would have been programme-defining — with rig time, mobilisation costs, and campaign schedule all at risk.

Phase identified and resolved the conflict onshore before a single day of rig time was committed.

The Solution

Bespoke Frame Design

Phase designed a bespoke support frame that straddled the Normar Carrier — allowing the subsea trees to be lifted into the moonpool and land on their funnels.

Removable guidance posts fitted to the frame provided safe restraint for transporting the carrier back to the setback area, where the trees were lifted off by crane.

The frame was designed to work within the height and width constraints of the moonpool — constraints that are not always visible until the physical conditions are verified.

Manufacture Management & Delivery

Phase oversaw the fabrication, painting, and delivery of the frame to the rig. Installation on the carrier used the retractable angel wings on the Normar Carrier as support. When the frame landed on the carrier it fitted exactly as designed — no adjustment required, no issues on installation.

Storyboard, Renders & Animations

Phase storyboarded the entire operation — producing rendered images and animations of the full deployment sequence including the AGR CWOR subsea stack consisting of EDP and LRP for VXT removal. All parties were aligned around a shared, verified understanding of the operation before mobilisation. No physical surprises offshore.

Related Work

Our Experience

The campaign in numbers

Campaign Duration

180

Days

Subsea Trees Retrieved

7

Successful Recoveries

Interface Conflicts Resolved

10

Surprises Offshore

Why It Mattered

Moonpool geometry and available handling equipment are not always fully understood by subsea engineers and operators ahead of a campaign.

Phase exists to fill that gap — establishing what’s physically possible before commitment is made, and resolving conflicts before they become offshore problems.”

What Made The Difference

The critical finding — that the trees could not be lifted using the existing carrier — was identified onshore through verified scan data and interface checks. Without that verification, the conflict would have surfaced offshore during a live decommissioning operation. The bespoke frame that resolved it was designed, manufactured, and delivered before the campaign began.

Shared Understanding Before Mobilisation

Every party involved in the campaign — Stena, AGR, and the operational crew — understood exactly how the operation would proceed before anyone went offshore. The storyboard, renders, and animations Phase produced ensured there were no unknowns in the room when mobilisation was committed.

The Result

Seven subsea tree retrievals. One hundred and eighty days offshore. Zero physical surprises. The frame fitted like a glove

A campaign that cannot afford surprises

If your rig-to-subsea campaign carries physical risk — fit, clearance, handling sequences, or interface compatibility — a short conversation is often enough to establish whether Phase can help.